Phase 0 - Roadway, front entrance, and new security booth and gate
- Zoning Complete –September 2021
- Permits complete – December 2021
- Construction Commences –February 2022
- Construction Complete –May 2022
Phase 1A - Relocate Andrews House, build temporary roadway from the Bradley Boulevard entrance to the Stadium and around outside of the BAC, remove the roadway between Torrey Hall and Andrews House, and adjust the topography for the new upper school building. Begin BAC addition.
- Design Complete – January 2022
- Permits Complete – April 2022
- Construction Start – June 2022. Ideally, will begin mobilization, trailer set up, and pre sediment erosion control meetings in May 2022. We are currently building out a schedule that includes the Andrews House renovation once the relocation is complete. We will base Andrews House re-occupancy on that schedule.
- Construction Complete –September 2022
Phase 1B - Construct a new courtyard and additional shells to the BAC addition, construct the new upper school building, new quad pathways, and construct bear circle
- Phase 1B Construction Start – June 2022. Plan is to begin mobilization, trailer set up, and pre sediment erosion control meetings in May 2022.
- Phase 1B BAC Addition Shell Complete – February 2023
- Phase 1B Upper School Construction Complete – August 2023
Phase 1C – Fully renovate the BAC and interior construction of the BAC addition, renovate the Wilson building, and renovate the existing middle school building to become the new lower school building
- Phase 1C Construction Start - June 2023
- Phase 1C Construction Completion – August/September 2023